Project Description
When upgrading the heating plant, the following equipment and work were delivered in stages:
10.5 KV and 6.3 KV substation
0.48 kV LV main switchboard
Subsidiary switchboards for boilers K6 and K7
Output of TG 3 power and replacement of electrical protection
Compensation switchboards for 3 cooling tower fans
Switchboards for external fuel management
Upgrading of the existing TG 1 2 – excitation sets
Adjustment of electric circuits for a new control system
Modernisation of the 220 V DC voltage system
Synchronisation
Switchboards for chemical water treatment plant
Control systems for the electrical parts
Connection of equipment to the control system