Project Description
Repair of the electrical parts
The project included:
Development of project implementation documentation
Supply and installation of a new 22 KV cabinet switchboard
Connection of a new 22 KV switchboard to the existing external HV network
Replacement of external surge arresters on outdoor air inlet lines
Connecting a new measurement field to the existing monitoring system of power consumption
Connecting the existing transformers from the new 22 KV switchboard
Supply of 1 secondary starter for 6 KV engine
Dismantling of an old 22 KV cubicle type switchboard